Planned Service Outage

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Plnd Outage
Posting Date/Time: 08/24/2019 13:45
Notice Effective Date/Time: 08/28/2019 09:00
Notice End Date/Time: 08/30/2019 08:59
Notice ID: 9377
Notice Status Desc: Supersede
Prior Notice: 9375
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: Southeast Area Capacity Reduction - Eunice Total (Updated 8/24/19) Update: Effective 8/24/2019 ID2, ANR will continue planned maintenance in the Southeast Area. (See PSO ID #9377)
Notice Text:
Southeast Area Capacity Reduction - Eunice Total (Updated 8/24/19)

Update: Effective 8/24/2019 ID2, ANR has complete planned compressor maintenance in its Southeast Southern Segment (Zone 2), but will continue planned compressor maintenance in its Southeast Area (Zone 1).

ANR will limit deliveries at the Eunice Total Location (LOC #505592) by 125-MMcf/d (leaving 1,050-MMcf/d available) for 8/28 - 8/29.

Since the last posting, ANR has removed the capacity restriction for 8/24 - 8/26 (effective 8/24 ID2) and updated the impact statement below.

Based on current nominations, it is anticipated that this posting may result in the capacity allocation reduction of IT, Firm Secondary and possibly a portion of Firm Primary volumes. Since ANR anticipates that this restriction may impact its ability to deliver all nominated Firm Primary services, ANR will apply the Reservation Charge Crediting Mechanism of Section 6.36.4 as necessary.

The estimated impact to Firm Primary is as follows:

8/28 - 8/29

0% - Based on the Current Net Shipper Nominations
11%- Based on the Current Contracted MDQ


Additionally, customers downstream of the Eunice Compressor Station may experience lower than normal pressure during the periods noted above. This posting will be updated as more information becomes available.

For additional planned outage information, please see the ANRPL System Maintenance Schedule on anrpl.com under Quick Links.

For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:

1-800-827-5267

Please contact System Operations with any questions regarding operations or facilities.
Monica Edwards 832-320-5822 Operations Control
Howard Earl 832-320-5855 Gas Control