Critical Notice

TSP:006958581
TSP Name:ANR Pipeline Company

Notice Type Desc: Plnd Outage
Posting Date/Time: 08/16/2019 13:15
Notice Effective Date/Time: 09/04/2019 09:00
Notice End Date/Time: 09/11/2019 08:59
Notice ID: 9363
Notice Status Desc: Initiate
Prior Notice:  
Reqrd Rsp: 5
Rsp Date/Time:  
Subject: SW Area Capacity Reduction (Posted 8/16/2019) New: ANR will begin planned maintenance at its Meade Compressor Station. (See PSO ID # 9363)
Notice Text:
SW Area Capacity Reduction (Posted 8/16/2019)

New: ANR will begin planned maintenance at its Meade Compressor Station, located in the Southwest Area (Zone 4). As a result, ANR will reduce the capacity at the following locations for 9/4 - 9/10:

E.G. Hill from Gageby (LOC #226643)
Reduced by 25-MMcf/d (leaving 200-MMcf/d available)

Beaver-CIG (REC FR CIG) (LOC #16435)
Reduced by 40-MMcf/d (leaving 120-MMcf/d available)

Greensburg/CP (REC) (LOC #385402)
Reduced by 570-MMcf/d (leaving 75-MMcf/d available)


Based on current nominations, it is anticipated the above reductions will result in the curtailment of nominations associated with IT and Firm Catalog Receipt points in the affected area. Also, interconnects along this segment may experience higher line pressures.

The estimated impact to Firm Catalog Receipts for 9/4 - 9/10 is as follows:

E.G. Hill from Gageby (LOC #226643)

10% - Based on the Current Net Shipper Nominations
15%- Based on the Current Contracted MDQ

There is no impact to Firm at Beaver-CIG (REC FR CIG) (LOC #16435) or Greensburg/CP (REC) (LOC #385402) .

This posting will be updated as more information becomes available.

For any questions regarding nominations or scheduling, please call the ANR Noms and Scheduling Hotline at:

1-800-827-5267

Please contact System Operations with any questions regarding operations or facilities.
Monica Edwards 832-320-5822 Operations Control
Howard Earl 832-320-5855 Gas Control